Project Gallery

KLOOF MINE
  • Shaft pillar steelwork – 260 ton (no 1 sub vertical shaft) - 2005
  • Shaft pillar steelwork – 235 ton (no 2 sub vertical shaft) –2006
ROYAL BAFOKENG RASIMONE MINE
  • Underground conveyors 212 ton –2005
  • Bulkhead Steelwork 120 ton -2005
  • Plate work chutes & grizzles -2005
  • Bulkhead Steelwork 120 ton –2006
  • Load bins 80 ton –2006
  • Station Steelwork 65 ton –2006
READ SWATMAN & VOIGHT
  • RSV 2007
  • Underground Bulkheads & Conveyors
  • 320tons
ELB 2007
  • VOORSPOED MINE
  • Overland Conveyors. Transfer Towers
  • 320ton
MURRAY & ROBERTS 2007
  • IMPALA PLATS
  • 5 Deck sinking stage
  • 94tons
SMEI 2008 – 2009
  • Impala Plats
  • Overland Conveyors: 6off
  • Transfer Tower: 8off
  • 372tons
DRA 2010 FOR DRC
  • Overland Conveyors 12off
  • Bin & Transfer Towers
  • 360ton
VOORSPOED MINE 2011
  • Waste dam Conveyor and Tripper
  • 111ton
BAMBANANI WEST SHAFT – HARMONY 2011
  • Surge Bin & Shaft Steelwork
  • 268ton
MURRAY & ROBERTS CEMENTATION 2012
  • 5 Deck sinking stage 94ton
  • Cirb Ring & Shutter 30ton
BAMBANANI EAST - HARMONY 2013
  • Shaft steel work
  • 354ton
JOEL MINE – HARMONY 2013
  • 136LEV Conveyors & Steelwork
  • 126ton
GREENSTONE 2015
  • Re-claim ore-bin
  • 218ton
FINSCH MINE 2015
  • Underground conveyors CV02
  • Bulkhead Steelwork
  • Tip steelwork
  • 384ton
FINSCH MINE 2016
  • Bulkhead 1A Steelwork & Platework
  • 184ton
KOFFIEFONTEIN MINE 2016
  • Bulkhead steelwork
  • Bins & Chutes
  • 211ton
FINSCH MINE 2017
  • Underground steelwork
  • Bins & Chutes
  • 284ton
  • Tip Steelwork
  • Tip Barrier Walls